Heating

Display:

The church's oil-fired heating boiler, installed 35 years previously, had come to the end of its working life and spare parts were no longer available. The churchwardens sought permission to replace the boiler with a new gas boiler. The Diocesan Advisory Committee expressed its disappointment that the church had not opted for a more environmentally friendly heating system. The Chancellor granted a faculty, being satisfied that the petitioners had considered the Church of England's 'Net Zero Roadmap' and the Church Building Council's guidance, and that the petitioners had also considered several alternative options, which had been discounted for various reasons, including costs, aesthetic considerations, and the potential impact of the different proposed solutions on the fabric and special character of the Grade I listed building. The Chancellor made it a condition of the faculty (inter alia) that so far as was practicable, gas supplied under a green tariff was to be used for the new system.

The proposed works to the church comprised electrical rewiring and new lighting; the installation of an audio-visual system; and a new heating system. The Diocesan Advisory Committee had some concerns about the proposal to install roof-mounted horizontal low temperature hot water radiant panel heaters. The Chancellor decided that the petitioners had shown a convincing argument for each part of the scheme and he granted a faculty.

The petitioners wished urgently to install in the church a new gas boiler, to replace the existing 35 years old boiler (which had been condemned) and to make improvements to the heating system and boiler room. The Diocesan Advisory Committee did not approve the proposal. It took the view that the petitioners had not fully considered the alternatives to using fossil fuel. The Deputy Chancellor granted a faculty, being satisfied that the petitioners had in fact considered all the available alternative heating systems, and that the system proposed was the only viable option that the church could afford. The Faculty was to be subject to a condition that the church either switched to a green gas tariff or entered into a separate arrangement with a carbon off-setting scheme to offset the carbon emissions from all non-renewable gas used.

The petitioners sought permission to replace a gas fired cabinet heater in the church with a new condensing gas heater. The Parochial Church Council had looked carefully at the alternative options. Heat pumps were not viable. It would be a possible alternative to install electric heaters, but these would be very expensive to install, less energy efficient, unsightly and expensive to run. The Diocesan Advisory Committee had certified that the petitioners have considered the Church of England’s net zero guidance, and they recommended the proposals. The Chancellor granted a faculty, without imposing a condition regarding carbon offsetting.

An application was made for a faculty for the replacement of the existing convection gas heaters with nine new convection gas heaters. The parish had obtained a quotation in the sum of £33,795.60. Of concern to the Chancellor was that the parish had already paid a deposit of £17,000 to the contractor before applying for a faculty, and when the application was made it was clear that the parish had not had “due regard” to the Church of England’s Net Zero policy by considering other options which did not involve replacing one fossil fuel system with another. The Chancellor required the petitioners to look at other options, which they did. The Chancellor, whilst deprecating the way things had been done, acknowledged that to reject the proposals would cause undue further financial problems for the church and a delay in providing a new heating system. He therefore granted a faculty, subject to conditions requiring the parish to enter into a green gas tariff or a separate arrangement with a carbon offsetting scheme and to obtain professional advice about how to make a meaningful contribution to Net Zero.

The proposals included an accessible toilet within the west tower, removal of the pews, new stone flooring and a new heating system including underfloor heating and perimeter radiators heated by a replacement gas boiler. There was opposition from the statutory consultees. The Chancellor had to consider whether the petitioners, as required by the Faculty Jurisdiction Rules 2015, had given 'due regard' to the net zero guidance on reducing carbon emissions issued by the Church Buildings Council. The Chancellor granted a faculty, being satisfied that the petitioners, through their heating consultant, had considered all alternative sources of heating and that "at the present time, a replacement gas boiler is the only viable and affordable heating option which will meet all the relevant needs and aspirations of the church".

Faculty granted for Air Source Heat Pumps, to replace an old electric boiler heating system.

The petition requested a confirmatory Faculty to regularize the unlawful installation of 6 combination light and heating chandeliers to replace the previous chandeliers and the current oil-fired heating system. The new chandeliers had been installed after the proposals had been recommended by the Diocesan Advisory Committee, but before the petition had been referred to the Chancellor. There was one party opponent. The Chancellor considered that the new chandeliers were not quite as attractive as the ones they replaced, but were efficient and cheap to run. He was, however, concerned that the new wiring was “deplorable”. He granted a faculty, subject to conditions that steps should be taken to mitigate the damage cause by the wiring; photographs of the original chandeliers should be archived, and the original chandeliers should then be sold.

The Parochial Church Council wished to install an oil condenser boiler in a position outside the church which would be screened from view. The new boiler would replace a boiler system installed in 2019, which by 2022 had become unusable. Attempts had been made to correct defects, but without success. In spite of an objection to the contrary, the Chancellor was satisfied that the PCC had considered alternative eco-friendly options. An electrical heating system was not possible as the electricity supply to the church was inadequate. Although oil would be used for the new boiler system, the PCC envisaged converting to biofuel when available. The Chancellor granted a faculty for 5 years, with liberty to apply at the end of that period for an extension, when consideration would be given as to whether biofuel or an improved electrical supply would be available at that time.

The Chancellor granted a faculty for a new heating system.